Electrical Infrastructure

Substation + HV Line Dhahran 2

Dhahran, Saudi Arabia

Project description

Construction of GIS (Gas Insulated Switchgear) Substation, 67 MVA 115 kV for National Grid Saudi Arabia. Substation nº1, 115/13.8 kV, 67 MVA. DHO #2 National Grid, S.A. (Saudi Arabia). EPC contract for three 115/13.9 kV GIS technology transformer substations, each equipped with three 57/67 MVA ONAN/ONAF transformers, for a total of 600 MVA. The three substations are integrated in the global project for a new residential area in Dhahran, financed by SAUDI ARAMCO, and under the technical supervision of NATIONAL GRID, S.A., all for integration into the electricity distribution network of SAUDI ELECTRICITY COMPANY.